Yes- It is called a Report and Consent for Demolition, but we will do this on your behalf.
It will take up to 3 to 4 weeks to obtain your Demolition Permit.
Contact your Gas and Electricity Company and inform them you need to have both utilities cut off for Demolition of your property. This can take up to 28 days to be completed so you need to do this urgently and take notes of whom you spoke to etc.
No we will need running water on site to keep the dust down while we are demolishing your property to protect the neighbouring properties from flying particles and dust, this is part of OH+S.
As soon as we have your Demolition Permit and all your Abolishment’s are disconnected and your temp fence has you been erected – we will arrange a convenient date with .
If your home has asbestos it will be removed before demolition by a registered asbestos removal company contracted by Ultimate Demolitions as part of your Quote.
Your temp fence must be erected before demolition begins, we recommended you contact Temporary Fence Hire companies to book a date after your Gas + Electricity have been abolished.
An average 4 bedroom home takes about 2-3 days for a clear site ready for building including all tree and stump removal. But each house can vary depending on individual circumstances.
Payment is due on completion of demolition, unless prior arrangements have been made within the contracts.
No. Once the house has been Quotes and Contracts have been signed all items of the house structurally become the property of Ultimate Demolitions and will be salvaged and recycled to designated companies for re-use. If you require special items from your home you must discuss this before contracts are signed.